Estimasi Biaya Konstruksi Berdasarkan Eskalasi Biaya pada Pembangunan Bendungan Tipe Urugan dengan Regresi Linier Berganda

Authors

  • Alfriady Zuliansyah Universitas Tarumanegara
  • Denik Sri Krisnayanti Universitas Tarumanegara
  • Wati Asriningsih Pranoto Universitas Tarumanegara

DOI:

https://doi.org/10.55606/jcsr-politama.v4i2.6385

Keywords:

Construction Cost, Diversion Channel, Embankment Dam, Multiple Linear Regression, Reservoir Storage Capacity

Abstract

Construction cost is one of the most important aspects determining the success of dam construction projects because it is directly related to project planning, budgeting, and cost control during implementation. Inaccurate cost estimation may lead to budget overruns, project delays, and reduced construction quality. This study aims to analyze the influence of reservoir storage capacity and diversion channel length on the construction cost of embankment dam projects using the multiple linear regression method. The research data were obtained from several embankment dam projects and analyzed using IBM SPSS Statistics software. The analytical procedures included classical assumption tests consisting of normality, multicollinearity, heteroscedasticity, and autocorrelation tests, followed by multiple linear regression analysis, partial significance tests, simultaneous significance tests, and coefficient of determination analysis. The results indicate that reservoir storage capacity and diversion channel length have a positive and significant effect on construction costs. The resulting regression equation is Y = 636.397 + 6.471X₁ + 0.960X₂, indicating that increases in reservoir storage capacity and diversion channel length will increase the construction cost of embankment dam projects. Both independent variables have significance values below 0.05, indicating that the proposed hypotheses are accepted. The developed regression model can be used as a reference for preliminary cost estimation of embankment dam projects, thereby supporting more effective, efficient, and accurate budgeting during the planning stage.

Downloads

Download data is not yet available.

References

Aditya, H., & Putra, A. (2025). Identification of factors causing cost increases in infrastructure projects. Eduvest – Journal of Universal Studies, 5(2), 1425–1436. http://eduvest.greenvest.co.id

Ansar, A., Flyvbjerg, B., Budzier, A., & Lunn, D. (2014). Should we build more large dams? The actual costs of hydropower megaproject development. Energy Policy, 69, 43–56. https://doi.org/10.1016/j.enpol.2013.10.069

Ashworth, A. (1994). Cost studies of buildings. Longman.

Asiyanto. (2011). Metode konstruksi bendungan. UI Press.

AWI Engineering and Consulting Plc. (2006). Design guideline for embankment dams for irrigation purpose.

Ghozali, I. (2011). Aplikasi analisis multivariate dengan program IBM SPSS 19 (5th ed.). Badan Penerbit Universitas Diponegoro.

Gill, A. S., Visotsky, D., Mears, L., & Summers, J. D. (2017). Cost estimation model for polyacrylonitrile-based carbon fiber manufacturing process. Journal of Manufacturing Science and Engineering, 139(4). https://doi.org/10.1115/1.4034713

Gunduz, M., & Sahin, H. B. (2015). An early cost estimation model for hydroelectric power plant projects using neural networks and multiple regression analysis. Journal of Civil Engineering and Management, 21(4), 470–477. https://doi.org/10.3846/13923730.2014.890657

Hase, N., Maizuar, M., & Jalil, A. (2024). Risiko cost overrun dalam pelaksanaan proyek konstruksi gedung di Provinsi Aceh. Jurnal Arsip Rekayasa Sipil dan Perencanaan, 7(1), 53–62. https://doi.org/10.24815/jarsp.v7i1.36823

Kementerian Pekerjaan Umum dan Perumahan Rakyat. (2022). Rampung tahun depan, Bendungan Keureuto mampu kendalikan banjir dan penuhi kebutuhan air di Aceh Utara. https://pu.go.id

Kerzner, H. (2017). Project management: A systems approach to planning, scheduling, and controlling (12th ed.). Wiley.

Khatsuria, R. M. (2004). Hydraulics of spillways and energy dissipators. CRC Press.

Kim, K. J., Kim, K., & Kang, C. S. (2009). Approximate cost estimating model for PSC beam bridge based on quantity of standard work. KSCE Journal of Civil Engineering, 13(6), 377–388. https://doi.org/10.1007/s12205-009-0377-0

Knutson, K., Schexnayder, C. J., Fiori, C. M., & Mayo, R. E. (2004). Construction management fundamentals. McGraw-Hill.

Kompas.com. (2019). Anggaran infrastruktur 2019 tembus Rp415 triliun. https://properti.kompas.com

Kompas.com. (2021). Pemerintah siapkan Rp384,8 triliun untuk pembangunan infrastruktur tahun anggaran 2022. https://nasional.kompas.com

Kontan.co.id. (2023). Pemerintah anggarkan Rp422,7 triliun untuk sektor infrastruktur di RAPBN 2024. https://nasional.kontan.co.id

Lembaga Ketahanan Nasional Republik Indonesia. (2021). Lemhannas RI bekerja sama dengan CSIS dan Kompas luncurkan buku Indonesia Menuju 2045. https://lemhannas.go.id

Macan, T. H. (1994). Time management: Test of a process model. Journal of Applied Psychology, 79(3), 381–391. https://doi.org/10.1037/0021-9010.79.3.381

Mahyuddin, Ritnawati, Rachim, F., Erdawaty, Pandarangga, A., Ulfiyati, Y., Sidiq, R., & Rosyta, A. (2023). Manajemen proyek konstruksi. Penerbit Widina.

Marshall, R. A. (2007). The contribution of earned value management to project success on contracted efforts (Master's thesis). University of Pretoria.

Olawale, Y. A., & Sun, M. (2010). Cost and time control of construction projects: Inhibiting factors and mitigating measures in practice. Construction Management and Economics, 28(5), 509–526. https://doi.org/10.1080/01446191003674519

Petheram, C., & McMahon, T. A. (2019). Dams, dam costs and damnable cost overruns. Journal of Hydrology X, 3, 100026. https://doi.org/10.1016/j.hydroa.2019.100026

Phaobunjong, K. (2002). Parametric cost estimating model for conceptual cost estimating of building construction projects (Doctoral dissertation). Virginia Polytechnic Institute and State University.

Pratiwi, R. E. (2012). Analisis pengaruh cost management terhadap efisiensi pada proyek konstruksi: Studi pada PT Adhi Karya (Persero) Tbk. Jurnal Ceylan, 21(2).

Project Management Institute. (2000). A guide to the project management body of knowledge (PMBOK® Guide).

Project Management Institute. (2013). A guide to the project management body of knowledge (PMBOK® Guide) (5th ed.).

Project Management Institute. (2021). A guide to the project management body of knowledge (PMBOK® Guide) (7th ed.).

Pusat Pendidikan dan Pelatihan Sumber Daya Air dan Konstruksi. (2016). Perencanaan bangunan utama bendungan.

Sejati, W., Pusoko, A. N. B. S., Aryadi, E. V., Andajani, S., Hidayat, D. P. A., Kurniyaningrum, E., & O'Connor, N. Z. (2024). Flood routing and dam breach parameter calculation on Sepaku Semoi Dam. Aptisi Transactions on Technopreneurship, 6(1), 136–148. https://doi.org/10.34306/att.v6i1.396

Turner, J. R., Grude, K. V., & Thurloway, L. (1996). The project manager as change agent: Leadership, influence and negotiation. McGraw-Hill.

TVOneNews.com. (2024). 10 tahun bangun infrastruktur, Jokowi habiskan anggaran segini: Apa saja wujudnya? https://tvonenews.com

United States Department of the Interior. (1987). Design of small dams (3rd ed.). U.S. Government Printing Office.

Vischer, D. L., & Hager, W. H. (1998). Dam hydraulics. John Wiley & Sons.

Wiryodiningrat, P. (1997). ISO 9000 untuk kontraktor. Gramedia Pustaka Utama.

Downloads

Published

2026-04-30

How to Cite

Alfriady Zuliansyah, Denik Sri Krisnayanti, & Wati Asriningsih Pranoto. (2026). Estimasi Biaya Konstruksi Berdasarkan Eskalasi Biaya pada Pembangunan Bendungan Tipe Urugan dengan Regresi Linier Berganda. Journal of Creative Student Research, 4(2), 362–378. https://doi.org/10.55606/jcsr-politama.v4i2.6385

Similar Articles

1 2 3 4 5 6 7 8 > >> 

You may also start an advanced similarity search for this article.