Perencanaan dan Pengendalian Jadwal Proyek Fiber To The Home Menggunakan Metode Program Evaluation and Review Technique dan Metode Predence Diagram Method di PT XYZ
DOI:
https://doi.org/10.55606/jtmei.v5i3.6386Keywords:
Critical path, Fiber To The Home, Precedence Diagram Method, Program Evaluation and Review Technique, Project durationAbstract
Fiber To The Home (FTTH) network construction projects require effective planning and schedule control to ensure completion within target timeframes. PT XYZ, a company specializing in the procurement of telecommunications goods and services, experienced delays in an FTTH project in West Sumatra. A project originally scheduled for completion in two months was delayed by up to four months due to the lack of a structured schedule and suboptimal time control. This study aims to determine the sequence of work activities, identify the critical path and project duration, and establish a more systematic basis for schedule control using the Program Evaluation and Review Technique (PERT) and Precedence Diagram Method (PDM). A quantitative descriptive approach utilizing a case study method was employed. Data were gathered through interviews with field supervisors, technicians, and project coordinators, as well as from company documents such as progress reports, working drawings, and technical project data. The results indicate that applying the PERT and PDM methods yields an estimated project duration of 41 days, which is faster than the two-month completion target. Furthermore, the use of Microsoft Project enables the systematic visualization of the project schedule, thereby facilitating more effective project time control.
Downloads
References
Abdurrasyid, Luqman, Haris, A., & Indrianto. (2020). Implementasi metode PERT dan CPM pada sistem informasi manajemen proyek pembangunan kapal. https://doi.org/10.23917/khif.v5i1.7066
Afifah, R. I. (2024). Analisis perancangan fiber to the home (FTTH) menggunakan software Optisystem pada Perumahan Kota Baru Graha Cemerlang (Skripsi sarjana, Universitas Hasanuddin).
Al Qordhowi, A. F. Y. (2023). Manajemen risiko dan kinerja proyek konstruksi. Jurnal Ilmiah Pendidikan Dasar, 8(1).
Anugerah, Z. S. P. (2021). Perancangan jadwal proyek untuk percepatan penyelesaian proyek fiber to the home menggunakan metode PERT, CPM, dan crashing lokasi Jl. Sukapura oleh PT XYZ (Skripsi sarjana, Telkom University).
Belferik, R., Andiyan, A., Zulkarnain, I., Munizu, M., Samosir, J. M., Afriyadi, H., & Prasetyo, A. (2023). Manajemen proyek: Teori & penerapannya. PT Sonpedia Publishing Indonesia.
Bere, G., Maulana, R., Ardian, O. H., & Sari, S. N. (2024). Analisis penjadwalan proyek menggunakan metode PERT (Proyek pembangunan Gedung DPRD Kabupaten Sleman Daerah Istimewa Yogyakarta). STORAGE: Jurnal Ilmiah Teknik dan Ilmu Komputer, 3(1), 63–71. https://doi.org/10.55123/storage.v3i1.3140
Durani, M. I. (2021). Perancangan jadwal proyek FTTH (Fiber to the Home) menggunakan metode Critical Path Method: Studi kasus pada PT XYZ (Skripsi sarjana, Telkom University).
Fadli, F. (2024). Analisis penjadwalan proyek pembangunan jaringan fiber optik menggunakan metode Critical Path Method (CPM) di Lemo-Lemo Bulukumba. Manufaktur: Publikasi Sub Rumpun Ilmu Keteknikan Industri, 2(3), 117–127. https://doi.org/10.61132/manufaktur.v2i3.510
Kerzner, H. (2017). Project management: A systems approach to planning, scheduling, and controlling (12th ed.). Wiley.
Mahjud, I., Nirwana, H., Andhika, A., Mimsyad, M., Litha, A., Yuniarti, Y., & Halide, L. (2022). Perancangan jaringan fiber to the home (FTTH) PT Telkom Indonesia (Persero) Tbk Witel Makassar di Desa Bontomanai Bulukumba. Jurnal Teknologi Elekterika, 19(2), 123–129. https://doi.org/10.31963/elekterika.v6i2.3803
Project Management Institute. (2017). A guide to the project management body of knowledge (PMBOK® guide) (6th ed.). Project Management Institute.
Project Management Institute. (2021). A guide to the project management body of knowledge (PMBOK® guide) (7th ed.). Project Management Institute.
Rahmana, A. (2026). Modul project management [Modul perkuliahan tidak dipublikasikan]. Universitas Widyatama.
Rofiq, M. F. (2020). Perancangan jadwal proyek untuk percepatan penyelesaian proyek fiber to the home menggunakan metode PERT-CPM dan crashing (Skripsi sarjana, Telkom University).
Roziya, N. A. (2021). Penerapan metode PERT dalam penjadwalan proyek telekomunikasi. Jurnal Teknik Elektro dan Komputer, 8(1), 45–54.
Soeparyanto, T. S., Nuhun, R. S., Ismayana, & Apriani, M. (2024). Penggunaan standar metode work breakdown structure (WBS) pada proyek pembangunan. https://doi.org/10.54297/sciej.v5i2.626
Stringer, Jusmidah, Fikri, M., & N. (2025). Analisis persepsi penerapan manajemen proyek terhadap keberhasilan proyek konstruksi. Jurnal Ilmiah Ecosystem, 25(1), 185–195. https://doi.org/10.35965/eco.v25i1.5869
Wijoyo, A., Kunaefi, A., Kurniawan, D., Zainudin, M., Gustamal, M. A., & Sulistiana, O. (2024). Fungsi organisasi pada manajemen proyek. OKTAL: Jurnal Ilmu Komputer dan Sains, 3(2), 537–541.
Winanto, S. (2024). Project management: Enhancing company resource efficiency and effectiveness. Jurnal Ekonomi, 13(1), 2406–2417.
Winata, D. H. (2021). Perencanaan penjadwalan waktu dengan metode PDM pada proyek pembangunan kantor perwakilan pemerintah daerah di Tapan (Skripsi sarjana, Universitas Bung Hatta).
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2026 Fauziah Nurcahya, Arief Rahmana

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.