Analisa Penjadwalan Produksi Dengan Metode Campbell Dudek Smith Untuk Meminimasi Makespan di CV. YZX

Authors

  • Muhammad Taufiq Universitas Pembangunan Nasional “Veteran” Jawa Timur
  • Endang Pudji Widjajati Universitas Pembangunan Nasional “Veteran” Jawa Timur

DOI:

https://doi.org/10.55606/jtmei.v2i4.2872

Keywords:

Production Scheduling, Working Time Measurement, Campbell Dudek Smith

Abstract

CV YZX is a manufacturing company in the stainless steel hardware sector that specializes in hardware and detailing. This company actively produces for the needs of individual consumers and orders from other companies. One of the problems faced by CV YZX is the use of production machines that are less than optimal at every stage of the production process. Production machine performance that is not optimal can increase the total value of production time (makespan), which in turn can cause delays in completing products and delivery to consumers. This research aims to find the minimum total production time value by applying the Campbell Dudek Smith method to production scheduling. The calculation results show that by applying the First Come First Serve (FCFS) production scheduling method, the company obtained a makespan of 39.64 hours. However, by using the proposed method, namely Campbell Dudek Smith (CDS) in production scheduling, the results of the makespan calculation show a figure of 33.58 hours. A comparison of the two methods shows that the proposed scheduling using the Campbell Dudek Smith method has a lower makespan value compared to the company method (FCFS), resulting in time savings of 6.06 hours or the equivalent of 15,3%.

References

Ambarwati, R, Supardi. 2021. Manajemen Operasi dan Implementasi dalam Industri. Magelang: Pusaka Rumah Cinta.

Antari, N., Harini, Tastrawati. N. 2021. Analisis Penjadwalan Produksi Menggunakan Metode Campbell Dudek Smith dan Dannenbring dalam Meminimumkan Total Waktu Produksi Beras. Jurnal Matematika, 10(4), 215-221.

Apnena, R. D., 2021. Optimasi Penjadwalan Flow Shop Perusahaan Garment dengan Metode Campbell Dudek Smith (CDS), Algoritma Nawaz Enscore Ham (NEH), dan Algoritma Pour dengan Kriteria Minimisasi Makespan. JIEE: Journal of Informatics and Electronics Engineering, 01(01), 32-35.

Arifandi, D., Lasalewo, T., Hasanuddin. 2022. Analisis Metode NEH Untuk Meminimalkan Makespan Pada Penjadwalan Produksi di Rumah Industri Wahyu. Jambura Industrial Review, 2(2), 65-74.

Aritonang, V. S. J. 2021. Perancangan Aplikasi Penjadwalan Produksi Dengan Menerapkan Metode CPM (Studi Kasus: PT. Indojaya Agrinusa Medan). KLIK: Kajian Ilmiah Informatika dan Komputer, 1(4), 148-153.

Ariyanti, S., Adianto, & Miharja, R. 2018. Usulan Penjadwalan Produksi Benang Menggunakan Metode NEH Dan Metode Algoritma Johnson Untuk Meminimasi Waktu Produksi Di PT. Laksana Kurnia Mandiri Sejati. Jurnal Ilmiah Teknik Industri, 6(3), 157 - 164.

Astuti, R. D., & Iftadi, Irwan. 2016. Analisis dan Perancangan Sistem Kerja. Yogyakarta: Penerbit Deepublish.

Cahyawati, A. N., Munawar, F. A., Anggraini, A., & Rizky, D. A. 2018. Analisis Pengukuran Kerja Dengan Metode Stopwatch Time Study. Jurnal Sentra, 4(2), 109.

Fradinata, E. 2022. Pesanan Pembelian Dalam Rantai Pasok. Aceh: Syiah Kuala University Press.

Haming, H. M., Nurnajamuddin, M. 2017. Manajemen Produksi Modern: Operasi Manufaktur dan Jasa Buku Edisi ke-3. Jakarta: PT. Bumi Aksara.

Hernanda, D. A., Hariastuti, N. L. P. 2022. Usulan Penjadwalan Produksi Pada Departemen Produksi PT. Preshion Engineering Plastec. Seminar Nasional Sains dan Teknologi Terapan. Institut Teknologi Adhi Tama Surabaya.

Hutabarat, J. 2017. Pengantar Teknik Industri. Malang: Media Nusa Creative.

Irawan, H. T.,Pamungkas, I., Arhami. 2020. Penjadwalan Produksi Paving Block Pada CV. Nibo Corporation Banda Aceh. Jurnal Optimalisasi, 6(1)

Kulsum, Utami, D. A. 2018. Usulan Perencanaan Penjadwalan Produksi Di Pt X. Journal Industrial Servicess, 4(1).

Nasution, R., Garside, A. K., Utama,D. M. 2017. Penjadwalan Job Shop Dengan Pendekatan Algoritma Artificial Immune System. Jurnal Teknik Industri, 18(01), 29-42.

Putra, B. I., Jakaria, R. B. 2020. Perancangan Sistem Kerja. Sidoarjo: UMSIDA Press.

Safitri, D. M., Rahmawati, N., Faradilla, A. 2021. Perancangan dan Pengukuran Kerja: Buku Ajar Kuliah Ergonomi dan Perancangan Sistem Kerja 1 Program Studi Teknik Industri. Makassar: PT. Nas Media Pustaka.

Suaryasa, G. N. I., Arnida, Adam, K. A., Mansur, D. M., Salijah, E., Yuswono, I., Puspasari, D., Nuryanto, U. W., Sabridah, Nafisa, L., Darsana, I. M., Yanto, F., Suwandaru, R., Amrullah, Y. A. 2023. Manajemen Operasi Pada Perusahaan. Bali: Intelektual Manifes Media.

Sulistiyadi, K. 2023. Ergonomi dan Pengukuran Kerja dalam Indusri. Yogyakarta: Jejak Pustaka.

Suradi. 2022. Sistem Produksi. Makassar: Tohar Media.

Tampubolon, F. R. (2021). Penyelesaian Penjadwalan Flexible Job Shop untuk Minimasi Due Windows dengan Algoritma Genetika. JISS: Jurnal Indonesia Sosial Sains, 2(6), 894-903.

Utama, D. M., 2023. Penjadwalan Teori dan Aplikasi. Malang: UMM Press.

Yanto. (2020). Konsep Dasar dan Aplikasi Statistika Inferensi Untuk Teknik Industri. Jakarta: Penerbit Atma Jaya.

Yohanes, A. 2014. Penjadwalan Produksi Di Line B Menggunakan Metode Campbell-Dudek-Smith (CDS). Jurnal Dinamika Teknik, 8(1), 7 – 15.

Downloads

Published

2023-11-13

How to Cite

Muhammad Taufiq, & Endang Pudji Widjajati. (2023). Analisa Penjadwalan Produksi Dengan Metode Campbell Dudek Smith Untuk Meminimasi Makespan di CV. YZX. Jurnal Teknik Mesin, Industri, Elektro Dan Informatika, 2(4), 11–14. https://doi.org/10.55606/jtmei.v2i4.2872