Analisis Penjadwalan Proses Produksi Billboard dengan Metode CPM (Critical Path Method)

Studi Kasus Pada Cv. Total Agra Mandiri di Kota Bandung

Authors

  • Gloria Wesuranaita Universitas Ekuitas Indonesia
  • Resi Juariah Susanto Universitas Ekuitas Indonesia

DOI:

https://doi.org/10.55606/jekombis.v5i1.5865

Keywords:

Billboard Production Scheduling, CPM, Critical Path, Production Efficiency, Project Scheduling

Abstract

This study analyzes the scheduling of billboard production processes at CV. Total Agra Mandiri in Bandung using the Critical Path Method (CPM) to identify production activities, determine critical paths, and compare production completion times. The research employed a qualitative method with a descriptive approach through interviews, documentation, and literature studies to obtain comprehensive data related to production scheduling. The findings indicate that the production completion time before the implementation of CPM was 27 days. After applying CPM, the production duration was successfully reduced to 25 days, demonstrating improved efficiency in production planning. The analysis also revealed that all production activities were included in the critical path with zero slack time, meaning that any delay in these activities would directly affect the overall production schedule. The identified critical paths were A–B–C–D–F–G–H–I–J–K and A–B–C–E–F–G–H–I–J–K. Therefore, these activities require strict monitoring and optimal control to prevent production delays and ensure timely completion of billboard production processes.

Downloads

Download data is not yet available.

References

Fadila, N., Suliawati, & Arfah, M. (2024). Analisis manajemen proyek dengan metode CPM (critical path method) pada pembangunan rumah subsidi di Perumahan Sultan Area City Kota Pinang. Factory: Jurnal Industri, Manajemen dan Rekayasa Sistem Industri, 3(1), 10–19. https://doi.org/10.56211/factory.v3i1.616

Fole, A., Mail, A., Safutra, N. I., & Nasrun, A. R. (2024). Evaluasi penjadwalan produksi dengan menggunakan metode Campbell Dudek and Smith (CDS) untuk mengoptimalkan waktu makespan pada UD Adi Utama. JIEI: Journal of Industrial Engineering Innovation, 2(1), 28–36. https://doi.org/10.58227/jiei.v2i01.117

Gultom, P., Simamora, E., Nehe, J. A., Tambunan, C. H., Purba, D. B., & Tamba, A. O. (2025). Penerapan metode jalur kritis (critical path method/CPM) dengan pendekatan kegiatan dan kejadian untuk perencanaan proyek. Ekopedia: Jurnal Ilmiah Ekonomi, 1(3), 511–520. https://doi.org/10.63822/bdd4r493

Halim, A. O., & Wicaksono, S. R. (2023). Rancang bangun sistem informasi produksi custom furniture berbasis web (studi kasus Jati Indah Furniture). Jurnal Teknologi, Informasi dan Industri, 6(2), 121–144. https://doi.org/10.33479/kurawal.v6i2.1044

Hasibuan, A., Ningtyas, C. P., Sirojudin, H. A., Saputra, J. I., Tahendrika, A., Fauzan, T. R., Yunani, A., Purnomo, A. C., Rahmawati, R., Rachmat, R. A., Nurdin, N., Sudrjat, Y., Marjuki, A., Friandi, S. Z., Sanni, M. I., & Hia, E. E. (2023). Manajemen produksi & operasi.

Julhadi, J., Susilawati, S., Rosa, S., Adriani, P., Ganiem, L. M., Fazilla, S., Aminy, M. H., Nurainiah, N., Syafrfuddin, S., Setyowidodo, A., Ririen, D., Diwati, F., Julyanti, E., & Ratnaningtyas, E. M. (2021). Metode penelitian pendidikan (N. Saputra, Ed.). Muhammad Zaini.

K, I. W., Cemang, M. R., Sari, Y. A., Sofan, M., & Surahman, G. (2025). 5663-Article text-9525-1-10-20251023. 9(3), 116–126.

Musfirah, A. W., Tenrisau, M. A., & Ramlawati. (2025). Pengaruh manajemen operasional di era digital dan perkembangan e-commerce. YUME: Journal of Management, 8(1), 1293–1298.

Nukuhehe, S., Saleh, L. M., & Gaspersz, W. (2025). Analisis penjadwalan proyek konstruksi dengan critical path method (CPM) pada proyek pembangunan Poliklinik Fakultas Kedokteran Universitas Pattimura Ambon. Jurnal Penelitian Multidisiplin Bangsa, 1(8), 965–976. https://doi.org/10.59837/jpnmb.v1i8.184

Nuraeni, N., & Santoso, B. (2024). Peranan manajemen persediaan bahan baku terhadap penjadwalan produksi PT XYZ. JURBISMAN: Jurnal Bisnis Manajemen, 2(2), 379–394.

Pradana, M. R., Setiawan, D., & Trinawati, L. (2023). Efektivitas ilusi 3D animasi Blender pada curved LED billboard (AB Building Jl. Juanda Pekanbaru). Jurnal Teknik Informatika, 3(2). https://doi.org/10.58794/jekin.v3i2.514

Sabita, F. A. (2024). Bab II tinjauan pustaka: Landasan teori manajemen operasi.

Sahril. (2022). Analisis manajemen waktu menggunakan metode CPM dan PERT pada proyek pembangunan jalan tol Pekanbaru–Bangkinang.

Sari, P. A., Febrianti, D., & Rahman, A. (2023). JITU (Jurnal Ilmiah Teknik Unida), 4(1), 43–52. https://doi.org/10.55616/jitu.v4i1.424

Sebayang, S. M., & Sondakh, E. (2023). Manufacturing center. Jurnal Logistik Bisnis, 13(2), 8–15.

Sihombing, Y. S. (2023). Analisis penerapan manajemen waktu pada proyek konstruksi dengan menggunakan jalur kritis/CPM (critical path method). Universitas Medan Area.

Sugiyono. (2020). Metode penelitian kuantitatif, kualitatif, dan R&D. Alfabeta.

Sugiyono. (2023). Metode penelitian kuantitatif, kualitatif, dan R&D. Alfabeta.

Downloads

Published

2026-02-19

How to Cite

Gloria Wesuranaita, & Resi Juariah Susanto. (2026). Analisis Penjadwalan Proses Produksi Billboard dengan Metode CPM (Critical Path Method) : Studi Kasus Pada Cv. Total Agra Mandiri di Kota Bandung. Jurnal Penelitian Ekonomi Manajemen Dan Bisnis, 5(1), 22–31. https://doi.org/10.55606/jekombis.v5i1.5865