Manajemen dan Pengawasan Proyek Rekonstruksi Jalan Geneng – Maron

Authors

  • Titan Adya Safara Institut Teknologi Sepuluh Nopember
  • Nur Ahmad Husin Institut Teknologi Sepuluh Nopember
  • Yudhi Arnandha Universitas Tidar
  • Budi Suswanto Institut Teknologi Sepuluh Nopember
  • Tatas Tatas Institut Teknologi Sepuluh Nopember

DOI:

https://doi.org/10.55606/juprit.v4i1.4767

Keywords:

project supervision, routine maintainance, road reconstruction

Abstract

Construction work or construction projects are a collection of complex tasks interconnected with each other. In its implementation, these construction projects must be adjusted to the plans that have been made, both in terms of volume, quality, cost, and time. The execution of these projects requires management and supervision by a supervisory team, which acts as a consultancy service provider to assist the Public Works and Spatial Planning Agency of Temanggung Regency. This project is the Reconstruction Package of the Geneng – Maron Road Section located in Temanggung Regency. Temanggung Regency is a regency located in Central Java Province which serves as one of the connectors between the Capital of Central Java Province and other cities or regencies. Road maintenance is carried out periodically as one of the efforts to maintain district roads. Routine road maintenance is carried out once a year, but for the improvement of the Geneng – Maron road section, it is carried out after the last improvement in 2016. Based on the Minister of Public Works Regulation No. 13/PRT/M/2011 regarding Procedures for Road Maintenance and Road Inspection, there is a table determining the road maintenance program for asphalt/concrete-covered roads, indicating that roads in severe disrepair should undergo reconstruction or improvement. The Geneng – Maron road itself is a district road frequently traversed by various classes of vehicles. However, the Geneng – Maron Road should have its status changed due to frequent passage by heavy-duty vehicles, causing it to deteriorate more rapidly due to its design and function being inadequate. Therefore, routine maintenance cannot be applied this year because the damage is already severe enough to require road reconstruction.

          

Downloads

Download data is not yet available.

References

Belferik, R., Andiyan, A., Syamil, A., Zulkarnain, I., Munizu, M., Samosir, J., Afriyadi, H., Rusmiatmoko, D., Adhicandra, I., Ichsan, M., & Prasetyo, A. (2023). Manajemen Proyek : Teori & Penerapannya.

Departemen Pekerjaan Umum. (2008). Pedoman Pengawasan Penyelenggaraan Pekerjaan Konstruksi.

Ervianto, W. I. (2023). Manajemen Proyek Konstruksi (L. Mayasari (ed.); 1 ed.). Andi Offset.

Herzanita, A., & Juwita, F. (2020). Perencanaan Perkerasan Jalan Beton Semen Portland Studi Kasus Peningkatan Jalan Way Sekampung – Sp. Bakauheni. Jurnal Teknika Sains, 05(01), 1–7.`

Kementerian PUPR. (2017). Modul Pemahaman Umum Pengawasan Konstruksi Pelatihan Pengendalian Pengawasan Pekerjaan Konstruksi.

Massie, M., Mannopo, F. J., & Ariestides. (2022). Studi Penerapan Pengendalian Waktu, Biaya, dan Mutu Pelaksanaan Proyek Boulevard Pantai Amurang Kabupaten Minahasa Selatan. Jurnal Ilmiah Media Engineering, 12(1).

Rahman, M. A., Arifin, H., & Sowolino, B. O. (2022). Perbandingan Metode International Roughness Index dengan Pavement Condition Index untuk Penentuan Kondisi Jalan Nasional di Kota Wamena (Studi Kasus : Ruas Jalan Wamena – Habema). Rang Teknik Journal, 5(1), 1–7. https://doi.org/10.31869/rtj.v5i1.2702

Santoso, J. (2021). Analisis Kondisi Struktur Jalan Bedasarkan Metode RCI (Road Condition Index) untuk Perencanaan Overlay Jalan [Universitas Medan Area]. https://repositori.uma.ac.id/jspui/bitstream/123456789/15657/1/168110102 - Jaya Santoso - Fulltext.pdf

Setiawan, F., & Ihsan, M. (2023). Pengendalian Waktu Pelaksanaan Project dengan Menggunakan Earned Value Concept. Jurnal Teknik Sipil Cendekia (Jtsc), 4(1), 474–520. https://doi.org/10.51988/jtsc.v4i1.125

Syammaun, T., Amin, J., & Bustami, B. (2021). Manajemen Risiko Proyek Konstruksi Jalan (Studi Kasus: Preservasi Rekonstruksi Jalan Lambaro – Bts. Pidie). Tameh: Journal of Civil Engineering, 8(2), 64–72. https://doi.org/10.37598/tameh.v8i2.77

Thoengsal, J. (2018). Manajemen Untuk Proyek Konstruksi.

Tjakra, J., & Inkiriwang, R. L. (2020). Pengendalian Biaya Struktur Konstruksi Beton Bertulang dengan Menggunakan Analisis Indeks pada Pembangunan Kalyana Residence Pall 2 Manado. Jurnal Sipil Statik, 8(4).

Yastawan, I. N., Wedagama, D. M. P., & Ariawan, I. M. A. (2021). Penilaian Kondisi Jalan Menggunakan Metode SDI (Surface Distress Index) dan Inventarisasi dalam GIS (Geographic Information System) di Kabupaten Klungkung. Jurnal Spektran, 9(2), 181–188.

Downloads

Published

2025-01-21

How to Cite

Titan Adya Safara, Nur Ahmad Husin, Yudhi Arnandha, Budi Suswanto, & Tatas Tatas. (2025). Manajemen dan Pengawasan Proyek Rekonstruksi Jalan Geneng – Maron. Jurnal Penelitian Rumpun Ilmu Teknik, 4(1), 131–151. https://doi.org/10.55606/juprit.v4i1.4767