Rencana Tahapan Penambangan Batubara Pada Tambang Terbuka Di Pit Selatan PT. RPP Contractor Indonesia Kecamatan Loa Janan Kabupaten Kutai Kartanegara Kalimantan Timur

Authors

  • Fauzan Dwi Syahputra Universitas Mulawarman
  • Shalaho Dina Devy Universitas Mulawarman
  • Henny Magdalena Universitas Mulawarman

DOI:

https://doi.org/10.55606/juprit.v3i3.4051

Keywords:

Design, Model Blocks, Work Hours, Loading Tools, Productivity

Abstract

In mining activities, especially in coal mining, of course there is a plan/design in mining activities that will be carried out such as production scheduling, fleet determination, to monthly/annual mining design stages. At PT.RPP Contractors Indonesia (RCI), precisely in the north pit, it has a production target that has been set, so it is necessary to phase out the mining plan to increase the planned production level and also to divide the entire volume in the pit limit into planning units that are smaller and easier to handle. To design a mining activity that will be carried out at PT.RPP Contractors Indonesia in making mining stages by making effective working hours or Standard Operational Parameters (SPO), determining the units to be used in mining activities, determining the fleet system and monthly design/ annual. The method used in making the mining phasing design is by making a block model for the bondary pit design and making schdulling stages in the software to facilitate the achievement of the production targets to be set. The results of the research resulted in mining stages in the Shorterm period (Quarterly) with estimated reserves of Overburden 713.000 BCM dan Coal 146.000 MT. Januari  203.917 BCM/44.500 MT, Februari 234.000 BCM/48.000 MT, Maret 265.000 BCM/54.000 MT with work units used 3 units of Excacvators and HD/dump trucks for OB removal and coal getting processes. With a 3 fleet system for stripping Overburden and Coal getting.

Downloads

Download data is not yet available.

References

Adnannnst, Maranto, & Donoguntoro. (2014). Rencana rancangan tahapan penambangan untuk menentukan target produksi PT. Cipta Kridatama Kecamatan Meureubo Kabupaten Aceh Barat Provinsi Aceh. Jurnal Pertambangan, ISSN: 2460-4699.

Arif, I. (2014). Batubara Indonesia. Jakarta: PT. Gramedia Pustaka Utama. ISBN: 978-602-03-0291-1.

Arif, I., & Adisoma, G. S. (2002). Perencanaan Tambang. Bandung: Institut Teknologi Bandung, Teknik Pertambangan.

Aryanda, D., Ramli, M., & Djamaudin, H. (2014). Perancangan sequence penambangan batubara untuk memenuhi target produksi bulanan. Bara 14 Seam C PT. Fajar Bumi Sakti, Kalimantan Timur. Jurnal Geosains, 10(2). ISSN: 1858-3636.

Bargawa, W. S. (2018). Perencanaan Tambang (Edisi Kedelapan). Yogyakarta: Kilau Book, Universitas Pembangunan Nasional Veteran Yogyakarta. ISBN: 9786237594314.

Fairus, S. A., Nurhakim, Saismana, U., & Nor, T. (2016). Perencanaan tahapan penambangan bulanan pada tambang terbuka batubara Open PIT. Teknik Pertambangan. Universitas Lambung Mangkurat. Jurnal Geosapta, 2(1). ISSN: 2460-3457.

Hartman, H. L. (1987). Introduction to Mining Engineering. Canada: John Wiley & Sons, Inc.

Haryono, A. F., Ariyanto, & Aprilianta, I. P. E. (2017). Perencanaan sequence penambangan batubara pada Seam 16 Phase 2 di PT. KTC Coal Mining & Energy, Kec. Palaran, Samarinda, Kalimantan Timur. (Unpublished).

Hustrulid, W., Kuchta, M., & Martin, R. (2006). Open Pit Mine Planning and Design Volume 1-Fundamentals (3rd ed.). London: Taylor & Francis. ISBN: 978-1-4665-7512-7.

Komatsu. (2013). Specification and Application Handbook (Edition 31). Jepang.

Mutia, N. (2020). Evaluasi realisasi penambangan batubara terhadap rencana blok penambangan PT. Bukit Asam Tbk. Jurnal Pertambangan, 4. Universitas Sriwijaya, Palembang. ISSN: 2549-1008.

Prodjosumarto, P. (2000). Diktat Kuliah: Pemindahan Tanah Mekanis. Bandung: Institut Teknologi Bandung.

Rasid, H., Handayani, E., & Bochori. (2019). Perencanaan teknis desain pit pada penambangan batubara di pit III. Jurnal Pertambangan, 3(2). ISSN: 2549-1008.

Read, J., & Stacey, P. (2009). Guidelines for Open Pit Design. Collingwood: CSIRO Publishing. ISBN: 978-0-415-87441-0.

Standar Nasional Indonesia. (2011). Pedoman Pelaporan Sumberdaya dan Cadangan Batubara (SNI 5015-2011). Badan Standarisasi Nasional.

Tenriajeng, A. T. (2003). Pemindahan Tanah Mekanis. Jakarta: Gunadarma.

Published

2024-07-19

How to Cite

Fauzan Dwi Syahputra, Shalaho Dina Devy, & Henny Magdalena. (2024). Rencana Tahapan Penambangan Batubara Pada Tambang Terbuka Di Pit Selatan PT. RPP Contractor Indonesia Kecamatan Loa Janan Kabupaten Kutai Kartanegara Kalimantan Timur . Jurnal Penelitian Rumpun Ilmu Teknik, 3(3), 01–09. https://doi.org/10.55606/juprit.v3i3.4051